School Board Meeting 8/12/2026

Full Video recording

Main Takeaways

  1. New renovation plans were presented - basically 70% new building, 30% old building. Will take about 3 years (Jan 2028 - Aug 2030, demolition ending Dec 2030). There'd be NO temporary classrooms; they will build a new classroom wing first over current blacktop area to move classes into. This plan retains both gym and library for most of the construction time; the library may move temporarily during phase 3. It COSTS MORE than a new building ($67.7 new vs $68.4 renovated). Final building will have less outdoor space (building is larger) that will be where the bike racks/front gym currently are. Outdoor space during construction will be limited.

    All board members feel this renovation is a good option as it means much less disruption to teachers/students than previously expected.

  2. Board is currently looking at $90 million + $17 million (from our savings) as the referendum amount. The vote is 6-1 (with Brett being the sole vote to want to ask for more to do more).

    Projects for this amount would include new middle school (68.4m), HS HVAC (35.5m), fire safety only at elementary schools (~3m). You can see a list of projects from April. This is basically lines 1 and 2, with a tiny bit of 3.

Additional documents/links

Important Dates

  • Next board meeting is Aug 19th. Referendum question will be finalized at this meeting.

  • The district’s annual meeting is scheduled for September 2. You can find the bulletin here, and it was mailed to all households in the last week or so.

Full Notes

These much abbreviated notes are for the full video recording. Time during meeting is included so you can skip ahead to the most interesting parts of the meeting with greater ease. Included are document links when relevant.

Survey Results - 6:35

Survey Results presentation and addendum

Focus Group themes - 42:43

Focus Group notes

New Renoation Plan - 50:30

Memo discussed right at the beginning. This links to many other documents on page 2.

New Renovation plan details

New Renovation floor plans

FInancial discussion of $90 million scope - 1:26:50

Lydell sidebar- 1:35:40

This discusses updates to Lydell as well as recaps the challenges the Lydell site has as a option for a new Middle School.

Board members discuss building new vs renvoation plan - 1:39:40

Priority of HS HVAC and other project priorities - 1:55:20

What's a good $ for the referendum - 2:05:00

Referendum question wording - 2:32:40

Public Comment - 2:36:50